FEPARA Project – Vale
Mining
Technical Sheet
End Customer

Vale

Contract period

November/22 to May/22

Scope of work

Independent Peer Review of Planning and CAPEX and Probabilistic Risk Analysis.

Description:
Earthmoving

63 MM m³

Railroad

363.1 km

Concrete

107,000 m³