Road works at Km 173, 180 and 499 – Teixeira Duarte
Infrastructure
Technical Sheet
End Customer

Teixeira Duarte

Location

Ponta Grossa/PR

Contract period

October/2020 to September/2021

Scope of work

Management of the Dynamic Planning System and participation in the Executive Management of the Implementation works of intersections km 173, km 180 and km 499, located in Ponta Grossa/PR.

Description:
Earthmoving

143,000 m³

CBUQ

3,330 t

Bored Pile

6,330 m

Reinforced earth wall

3,920m²